The installation and curing of the ALPHALINER at the construction site are quite straightforward, which allows for a fast resolution of the overall construction project. Up to 300 meters of sewer can be rehabilitated in a single day, and the sewer can be put back into operation in a very short time. This significantly reduces obstructions to traffic, construction noise and dirt.

1. Preparation of the sewer to be rehabilitated by cleaning and, if necessary, milling
2. First quality check: The condition of the sewer is recorded in a TV camera inspection
3. Preparing for installation: A foil is drawn into the sewer to protect the Alphaliner's outer skin
4. Drawing in the liner: Using a winch and a conveyor belt, if necessary, the Alphaliner is drawn through the manhole into the sewer section to be rehabilitated.
5. Second quality check: TV camera inspection with an UV light source to verify the position of the liner
6. Curing with a UV light source and a special UV lamp
7. Third quality check: The curing process is verified and documented online by means of the measured curing parameters.
8. Fourth quality check: Leakage test and taking of a construction-site sample for quality testing
9. Finishing: The liner ends are connected to the manhole, and the building laterals are cut open with a milling robot. The building laterals are connected either with a top-hat profile or by grouting
10. Fifth quality check: TV camera inspection with complete documentation